1. Project Cost
|
|
| |
Item |
Description |
Q’ty |
Cost |
Remarks |
1 |
GSE SP-25 SWH |
1 |
$1,400 |
|
2 |
Heat Exchange Tank |
|
$950 |
|
3 |
Pump |
|
$150 |
|
4 |
Controller |
|
$275 |
|
5 |
Drain Back Tank (or Glycol) |
|
$300 |
Drain back system or system with glycol. |
6 |
Installation Materials |
|
$400 |
|
7 |
Installation Labors |
|
$1,200 |
|
8 |
Ontario Rebate |
|
-$1,250 |
|
9 |
Federal Rebate |
|
-$1,250 |
|
10 |
Energy Audit1
|
|
$300 |
|
11 |
Energy Audit1 Rebate |
|
-$150 |
50%, up to $150 rebated by Ontario Government. |
12 |
Energy Audit2 |
|
$150 |
|
13 |
Total |
|
$3,975 |
|
|
|
| |
|
|
| |
2. Economic Analysis |
|
| |
| Item |
Description |
Results |
Remarks |
1 |
Project Cost |
$2,475 |
|
2 |
Annual Savings |
up to $220 |
One unit saves up to 400 m³ gas per year on optimized performance conditions, based on current gas price of $0.55/m³. |
3 |
Investment pay-back cycle |
around 11 years |
|
4 |
Equipment life cycle analysis: Total static benefit throughout 20 year equipment design life cycle |
$4,400 |
Gas price goes up every year. Your total benefit would be more than $4,400 in 20 year equipment life cycle. |
5 |
Environment contribution |
Yearly 0.7 tons of green-house gases reduced each unit. |